What's happening
King Street West returns to a construction zone on Nov. 23, when the City of Toronto and the TTC resume coordinated infrastructure work that will once again pull 504 and 304 King streetcars off the corridor and onto Queen Street West.
The City will lead the project's first phase, replacing two watermains that are 139 years old, according to the TTC's King Street West project page. Streetcar track renewal by the City and TTC will follow.
By pairing the watermain replacement with the track work, the two agencies said they can complete both upgrades at the same time and cut down on construction-related disruption for the surrounding neighbourhood in the years ahead.
Timeline and streetcar diversions
Service changes were already introduced on Nov. 1 to prepare for the watermain work. Beginning Nov. 23, crews will replace watermains on King Street West between Dufferin Street and Close Avenue, bringing additional route changes.
A second phase of watermain replacement, between Spadina Avenue and Portland Street, is expected to begin as early as December 2026, with its own service adjustments.
While construction proceeds, 504 and 304 streetcars will divert via Queen Street West. Wheel-Trans service will continue to operate throughout the work.
More TTC service changes are expected as construction progresses through 2027, particularly once the streetcar track renewal begins. The TTC said details will be posted to its project page once they are confirmed.
Queen Street West measures
To absorb the extra streetcar activity on the diversion route, the City will implement temporary transit priority measures on Queen Street West between Spadina Avenue and Roncesvalles Avenue, measures that were approved by City Council.
As early as Nov. 18, City crews will begin installing signage over several days for extended no-stopping prohibitions and new turn restrictions on Queen Street West between Roncesvalles Avenue and Shaw Street. Signage between Shaw Street and Spadina Avenue will go up at a later date.
The temporary measures will be removed once construction on King Street West is finished and the 504 and 304 return to their regular route.
Where to get updates
The TTC said residents and riders with questions can receive construction updates through the project page, and that the City of Toronto's King Street Construction webpage carries the latest schedules, work hours, travel impacts and progress reports.
Project information is also available in Filipino (Tagalog) and Tibetan through the notices section of the TTC page.